Abstract
In conventional concrete-encased steel composite columns, a steel section is placed at the center of the cross section. Thus, the contribution of the steel section to the overall flexural capacity of the column could be limited. For better efficiency and economy, particularly under biaxial moment, the steel section needs to be placed at the corners, rather than at the center of the cross section. Recently, a prefabricated steel-reinforced concrete column has been developed to utilize the advantages of the reinforced concrete column and the steel-concrete composite column. In the composite column, four steel angles are placed at the corners of the cross section, and transverse bars and plates are used to connect the angles by welding or bolting. The composite column has been widely applied to industrial buildings that require large sized columns and fast construction. In this chapter, the newly developed composite column is introduced, and basic mechanism, structural performance, and field application case are discussed.
Keywords
- metal and composite structures
- composite column
- steel angle
- weld connection
- bolt connection
- compression test
- flexural test
- cyclic test
1. Introduction
Nowadays, the demand for huge buildings, long-span structures, and skyscrapers has increased. As a result, (1) sectional performance of compressive members, and (2) fast and safe construction method become important. Figure 1(a) shows a conventional concrete-encased steel (CES) composite column using a wide-flange steel section at the center of the cross section. Generally, the wide-flange steel is placed at the center of the cross section, and then longitudinal bars and tie bars are placed in construction site. Thus, the contribution of the steel section to the overall flexural capacity of the column could be limited. Further, the need for rebar and formwork construction requires considerable construction time. Particularly, in mega structures such as semiconductor factory and warehouse using long and large sized columns, fast and safe construction methods are necessary.

Figure 1.
Comparison of CES column and PSRC columns. (a) CES composite column, (b) PSRC composite column (weld connection), (c) PSRC composite column (bolt connection).
In order to improve structural capacity and cost efficiency, a prefabricated steel-reinforced concrete (PSRC) composite column has been used. As shown in Figure 1(b) and (c), the prefabricated steel angles at the four corners replace the conventional wide-flange steel, and the steel angles are weld connected or bolt connected with transverse bars or plates [1, 2, 3, 4, 5]. The weld connection should follow the details prescribed in welding standards [6, 7]. The steel angles resist axial load and flexural moment. The transverse bars and plates provide shear resistance, concrete confinement, and bond resistance between the steel angles and concrete. Because the steel cage of angles and transverse reinforcement are prefabricated off site, field rebar work is unnecessary. Further, the self-erectable steel cage can provide sufficient strength and rigidity to support the construction loads of beams and slabs that are superimposed on the PSRC composite column.
Figures 2 and 3 show field application of weld-connected and bolt-connected PSRC composite columns, respectively. Generally, the PSRC composite column with 20 m height and 1.5 m × 1.5 m to 2.0 m × 2.0 m sectional area is used for two- or three-story construction at the same time. In the case of the weld-connected PSRC composite column, the steel cage of angles and transverse reinforcement is moved to construction site, and then concrete form is installed (Figure 2). On the other hand, in the case of the bolt-connected PSRC composite column, concrete form is preattached to the steel cage and it can be permanently used after concrete pouring (Figure 3). Thus, field work related to reinforcing bar placement and concrete form work is excluded, which improves the construction safety and saves the construction time at working in high place.

Figure 2.
Semiconductor FAB (weld-connected PSRC composite column).

Figure 3.
Semiconductor FAB (bolt-connected PSRC composite column).
2. Structural performance of PSRC column
2.1. Contribution of transverse reinforcement
The prefabricated steel angle composite columns strongly depend on the transverse reinforcement that connects the corner steel angles. The transverse reinforcement provides (1) shear transfer between the steel angles, (2) bond between the steel angles and concrete, (3) buckling resistance for the steel angles, and (4) lateral confinement for the core concrete. To satisfy the requirements of (3) and (4), close spacing as well as sufficient strength are required for the transverse reinforcement. However, the transverse bars welded to steel angles or the transverse plates bolt-connected to steel angles may cause premature tensile fracture of the connection, which should be considered in design.
Cover concrete provides local buckling resistance and fire resistance for the steel angles. However, when the transverse bars are not closely spaced, the PSRC composite columns are vulnerable to premature spalling of the cover concrete due to smooth surface of steel angles. Particularly, when the columns are subjected to high axial compression force, the load-carrying capacity and deformation capacity of the PSRC composite columns can be degraded by early spalling of the cover concrete. Further, under cyclic lateral loading, the PSRC composite columns are expected to be more susceptible to such damages as the ductility demand increases.
2.2. Compressive strength
2.2.1. Design method
The nominal compressive strengths
where
For better evaluation of the load-carrying capacity of a PSRC composite column, numerical analysis using the stress–strain relationship of confined concrete, unconfined concrete, and steel can be used as shown in Figure 4 [1, 3]. The numerical analysis can be performed using strain compatibility method [9]. The stress–strain relationship of confined and unconfined concrete can be determined from various existing models [10, 11, 12].

Figure 4.
Stress–strain relationships of concrete and steel for numerical analysis.
The nominal compressive strengths

Figure 5.
Section analysis methods of PSRC column under eccentric axial loading: (a)
2.2.2. Structural test
Figure 6 shows the test setup for the concentric axial loading and eccentric axial loading tests. The eccentricity can be controlled using the distance between the column center and loading center. During the test, the load-carrying capacity, axial shortening, and horizontal expansion were measured to evaluate the structural performance of the PSRC composite columns.

Figure 6.
Test setup of compressive loading tests: (a) concentric axial loading and (b) eccentric axial loading.
Figure 7(a) compares the axial load-strain relationships of a CES and PSRC composite columns using steel ratio of 2.0% under concentric axial compression force [3, 4, 5]. The axial load behavior of the PSRC composite column was similar to that of the CES composite column. The contribution of the steel angles to the lateral confinement increased the peak strength

Figure 7.
Axial load-carrying capacities of CES and PSRC columns: (a) concentric axial loading and (b) eccentric axial loading.
Figure 7(b) compares the
2.3. Flexural strength
2.3.1. Flexural design method
The ultimate flexural strength of a PSRC composite column can be evaluated by performing a section analysis based on either plastic stresses (i.e., plastic stress method) or strain-induced stresses (i.e., strain-compatibility method); the stresses of the steel angles, reinforcing bars, and concrete are determined by linear strain distribution and the stress–strain relationships of the materials [1]. Figure 8 shows the stress distributions at the PSRC cross section by two methods. For the plastic stress method (Figure 8(a)), plastic stresses of concrete, steel angles, and reinforcing bars can be used as 0.85

Figure 8.
Section analysis methods of PSRC column: (a) plastic stress method and (b) strain-compatibility method.
where
2.3.2. Shear design method
The shear resistance of a PSRC composite column is provided by concrete, transverse reinforcement, and steel angles. Since the dimensions of the angle cross section are significantly less than that of the entire cross section, the contribution of the angles to the shear strength is neglected. Thus, the nominal shear strength
where
2.3.3. Bond strength design method
Figure 9 shows the details of the weld- or bolt-connection between the steel angles and transverse reinforcement. Before spalling of concrete cover, the shear transfer between the steel angles and concrete is provided by friction of the angle surface and concrete bearing of the transverse reinforcement projected from the angle surface. Conservatively neglecting the frictional resistance, the nominal bond strength
where

Figure 9.
Bond strength between steel angle and concrete.
2.3.4. Structural test
Figure 10 shows the test setup for the flexural loading tests to investigate the flexural and shear strengths, shear transfer between steel angle and concrete, and strength at the joint between steel angle and transverse reinforcement. The columns are simply supported, and two-point loading is applied at the center of the columns. To estimate the curvature, deflections at least three points need to be measured.

Figure 10.
Test setup of flexural loading tests.
Figure 11(a) shows the moment-curvature relationships at the center span of a CES column and a PSRC column with a cross section of 500 mm × 500 mm (i.e., 2.0% steel ratio) [1]. In the PSRC column using the same steel ratio of the CES column, the peak strength was 56.7% greater than that of the CES column for the following reasons: (1) the yield strength of the steel angles used for the PSRC column was 15.9% greater than that of the wide-flange steel section used for the CES column and (2) the angles placed at the four corners of the cross section can develop 35.2% higher nominal flexural capacity than the center wide-flange steel section. In the PSRC column, the load-carrying capacity was suddenly decreased when bond failure (i.e., concrete bearing failure) occurred in the bottom angles in the shear span (Figure 12(b)). After the bond failure, dowel action of the transverse bars developed, causing significant bond-slip deformation. Ultimately, it failed due to the fracture of the transverse bars and spalling of web concrete, which was the typical bond-shear failure mode of the PSRC composite column.

Figure 11.
Moment-curvature relationships at the center span of CES and PSRC columns: (a) CES and PSRC columns; (b) PSRC columns according to transverse bar spacing.

Figure 12.
Failure modes of CES and PSRC columns. (a) CES column, (b) PSRC column, (c) PSRC column @ 100 mm tie, (d) PSRC column @ 200 mm tie, (e) PSRC column @ 300 mm tie.
Figure 11(b) compares the effect of transverse reinforcement spacing on the moment-curvature relationship of PSRC composite columns with a smaller cross section of 400 mm × 400 mm (i.e., 3.1% steel ratio). When the transverse reinforcement at a spacing of 100 mm was used, the load-carrying capacity was degraded due to spalling of cover concrete in the uniform moment span, but was slightly recovered due to the strain hardening of the steel angles. Ultimately, it failed due to the tensile fracture of the bottom angle in the uniform moment span (Figure 12(c)). The moment-curvature relationship and failure mode of the PSRC composite column with greater transverse reinforcement spacing of 200 mm were similar to those of the PSRC composite column with transverse reinforcement spacing of 100 mm. It failed due to tensile fracture of the angles in the uniform moment span (Figure 12(d)). In the PSRC composite column with the greatest transverse reinforcement spacing of 300 mm, bond failure occurred in the bottom angles. After the bond failure, the load-carrying capacity was significantly decreased due to spalling of web concrete caused by dowel action of the transverse reinforcement. Ultimately, it failed due to fracture of the transverse reinforcement (Figure 12(e)).
2.4. Seismic performance
Figure 13 shows the test setup of cyclic loading tests for CES and PSRC composite columns. Using two oil jacks, a uniform axial load corresponding to about 22% of compressive capacity are applied, and a cyclic lateral load is applied using an actuator to the column.

Figure 13.
Test setup of cyclic loading tests.
Figure 14 compares the cyclic behaviors of the CES and PSRC composite columns using steel ratio of 2.2%. In the CES composite column, the load-carrying capacity gradually decreased after the peak strength. Although spalling of the cover concrete occurred at the lateral drift of 3.0–4.0% in the plastic hinge region, the load-carrying capacity was not significantly decreased. However, after the spalling of the cover concrete, post-yield buckling occurred in the longitudinal bars. Ultimately, it failed at the drift ratio of 7.0% because of a low cycle fatigue fracture of the longitudinal bars. In the PSRC composite column, the peak strength was 20% greater than that of the CES composite column because of the higher yield strength and the location of the steel angles. Spalling of the cover concrete occurred at the drift ratio of 3.0%, and significant shear cracks occurred in the plastic hinge region because of the increased shear demand. The angles and transverse reinforcement were exposed because of the spalling of cover concrete at the drift ratio of 5.0%. The exposed angles and longitudinal bars were subjected to local buckling during repeated cyclic loading. As a result, the load-carrying capacity was degraded. However, despite the local buckling of angles and longitudinal bars, tensile fracture did not occur at the joint between the angles and transverse reinforcement.

Figure 14.
Lateral load-drift relationships of CES and PSRC columns: (a) CES column and (b) PSRC column.
2.5. Beam-column joint
2.5.1. Design method
Figure 15 shows a U-shaped composite beam-PSRC composite column connection. In order to minimize the workability problem during concrete pouring, only the web plate of the U-section is passed through the joint, and the top and bottom flanges are connected to the top and bottom band plates in the joint. Under high axial compressive force and cyclic lateral loading, premature cover concrete spalling of the joint may deteriorate the connection’s strength and deformation capacity.

Figure 15.
Beam-column joint details: (a) interior beam-column joint and (b) exterior beam-column joint.
Figure 16 shows the three mechanisms that contribute to the joint shear strength: web shear yielding of the U-shaped steel section (Figure 16(a)), direct strut action of the in-filled concrete inside the U-shaped section (Figure 16(b)), and the strut-and-tie action between the concrete (outside of the U-shaped section) and the band plates (Figure 16(c)) [2]. The shear strength
where

Figure 16.
Joint shear strength mechanisms. (a) Web shear yielding (
The shear strength
where
The shear strength
where
For the strut-and-tie mechanism in Eq. (14), the tension force caused by the concrete strut should be resisted by the top and bottom band plates. Thus, the required cross-sectional area
where 2
The joint shear capacity and demand can be expressed as moments, from the static moment equilibrium at the joint (Figure 16(e)).
where (Σ
2.5.2. Structural test
Figure 17 shows the cyclic lateral load-story drift ratio relationships of U-shaped steel composite beam-PSRC composite column joints. The composite beam has 330 mm width and 700 mm height including slab. The PSRC composite column has 800 mm × 800 mm cross-sectional area. In the interior beam-column joint, cover concrete spalling in the PSRC composite column occurred in the vicinity of the U-section, whose web plate buckled, and severe diagonal cracking occurred in the joint face. The fracture was initiated at the weld joint between the web and the bottom flange and then propagated vertically. Because the band plates were not connected to the bottom flange of the U-section, the band plates were not damaged even after cover concrete spalling. However, a gap occurred between the end of the U-section and the column face under positive moments, which was attributed to an anchorage slip of the web plates showing plastic strains inside the joint. As the anchorage slip increased, development of the beam’s flexural capacities was delayed, which caused significant pinching in the cyclic behavior. The top band plates welded to the top flange of the U-section were pulled out under a negative moment. In the exterior beam-column joint, after the peak strengths, the load-carrying capacity was significantly degraded because of cover concrete spalling in the PSRC composite column and because of local buckling and fracture of the web in the composite beam. The steel angles of the column were completely exposed.

Figure 17.
Lateral load-drift relationships: (a) interior beam-column joint and (b) exterior beam-column joint.
3. Conclusions
In this chapter, a prefabricated steel-reinforced concrete (PSRC) composite column using steel angles was introduced. Using current design codes, the structural capacities of PSRC composite columns can be evaluated, and it shows better performance than those of a conventional concrete-encased steel (CES) composite column.
The axial load-carrying capacity and deformation capacity of PSRC composite columns are comparable to, or even better than, those of conventional CES composite columns. In the PSRC composite column under axial compression, the corner angles and the transverse reinforcement provide adequate lateral confinement to the concrete.
The corner angles of the PSRC composite column increase the flexural strength and stiffness up to about 30%, compared to those of the conventional CES composite columns.
The bond strength between steel angles and concrete is generated by the bearing strength of the transverse reinforcement projected from the steel angle surface. When the bond strength is greater than the demand (i.e., when close spacing of tie bars is used), the PSRC composite columns show ductile behavior after flexural yielding without bond failure, and ultimately fail due to fracture of the steel angles. Otherwise, significant bond slip occurs in the steel angles, and ultimately the columns fail due to the bond failure of steel angles or the fracture of transverse bars.
Under cyclic lateral loading, the PSRC composite columns show about 20% lower deformation capacities than that of the conventional CES composite column. The lower deformation capacity of the PSRC composite columns is attributed to the following reasons: (1) relatively large plastic strains occur in the corner steel angles; (2) after spalling of the cover concrete, the exposed steel angles are susceptible to local buckling; and (3) the shear demand of the transverse reinforcement increases.
In composite beam-PSRC composite column joints, the load-carrying capacity decreases because of the web local buckling of the U-section at the column face. Ultimately, the beam-column joints fail because of a tensile fracture of the buckled web plates initiated at the weld joint between the web and the bottom flange of the U-section. As yielding occurs in the web plate of the beam, significant web plate anchorage slip occurs inside the joint. However, the anchorage slip mitigates possible stress concentration that may be caused by the discontinuity of the flange plate, which contributes to the increase in deformation capacity.
References
- 1.
Eom TS, Hwang HJ, Park HG, Lee CN, Kim HS. Flexural test for steel-concrete composite members using prefabricated steel angles. Journal of Structural Engineering. 2014; 140 (4):04013094. DOI: 10.1061/(ASCE)ST.1943-541X.0000898 - 2.
Hwang HJ, Eom TS, Park HG, Lee SH, Kim HS. Cyclic loading test for beam-column connections of concrete-filled U-shaped steel beams and concrete-encased steel angle columns. Journal of Structural Engineering. 2015; 141 (11):04015020. DOI: 10.1061/(ASCE)ST.1943-541X.0001242 - 3.
Hwang HJ, Eom TS, Park HG, Lee SH. Axial load and cyclic lateral load tests for composite columns with steel angles. Journal of Structural Engineering. 2016; 142 (5):04016001. DOI: 10.1061/(ASCE)ST.1943-541X.0001452 - 4.
Kim HJ, Hwang HJ, Park HG, Kim DK, Yang JM. Eccentric axial load test of prefabricated composite columns using bolt-connected steel angles. Journal of Korean Society of Steel Construction. 2017; 29 (3):249-260. DOI: 10.7781/kjoss.2017.29.3.249 - 5.
Kim HJ, Hwang HJ, Park HG, Kim DK, Yang JM. Axial load test of prefabricated composite columns using bolt-connected steel angles. Journal of Korean Society of Steel Construction. 2017; 29 (2):147-158. DOI: 10.7781/kjoss.2017.29.2.147 - 6.
AWS (American Welding Society). Structural Welding Code-Reinforcing Steel (AWS D1.4). Miami; 1998. 45 p - 7.
AWS (American Welding Society). Structural Welding Code-Steel (AWS D1.1). Miami; 2010. 540 p - 8.
AISC (American Institute of Steel Construction). Specification for Structural Steel Building (ANSI/AISC 360-10). Chicago; 2010. 610 p - 9.
Spacone E, El-Tawil S. Nonlinear analysis of steel-concrete composite structures: State of the art. Journal of Structural Engineering. 2004; 130 (2):159-168. DOI: 10.1061/(ASCE)0733-9445(2004)130:2(159) - 10.
Hognestad E. A study of combined bending and axial load in reinforced concrete members. In: Bulletin Series. Vol. 399. Urbana, IL: Univ. of Illinois Engineering Experimental Station; 1951 - 11.
Mander JB, Priestley MJN, Park R. Theoretical stress strain model for confined concrete. Journal of Structural Engineering. 1988; 114 (8):1804-1826. DOI: 10.1061/(ASCE)0733-9445(1988)114:8(1804) - 12.
Hoshikuma J, Kawashima K, Nagaya K, Taylor AW. Stress-strain model for confined reinforced concrete in bridge piers. Journal of Structural Engineering. 1997; 123 (5):624-633. DOI: 10.1061/(ASCE)0733-9445(1997)123:5(624) - 13.
ACI (American Concrete Institute). Building Code Requirements for Structural Concrete and Commentary. ACI 318-14. Farmington Hills, MI; 2014. 520 p - 14.
Eurocode 4. Design of Composite Steel and Concrete Structures-Part 1-1: General Rules and Rules for Buildings. Belgium: CEN; 2004. 122 p