Open access peer-reviewed chapter

Fuzzy Approach Model to Portfolio Risk Response Strategies

Written By

Yaser Rahimi

Submitted: 05 October 2020 Reviewed: 12 November 2020 Published: 23 December 2020

DOI: 10.5772/intechopen.95009

From the Edited Volume

Risk Management

Edited by Muddassar Sarfraz and Larisa Ivascu

Chapter metrics overview

419 Chapter Downloads

View Full Metrics

Abstract

Risk management and control of project risks have been the intrinsic characteristics of high-rise building projects in a changing built environment. In this research, a novel bi-objective model for the best mixture of projects is proposed. The first objective focuses on maximizing profits and efficiency of risk responses, and the second objective aims at minimizing project direct cost including machinery, human, and material costs to implement proper risk responses over a planning horizon under uncertainty. In this model, risks of the projects are controlled by time, quality, and cost constraints, and the most optimum risk response strategies (RRSs) are selected to eliminate or reduce the impacts of the risks. Thus, the combination of optimum projects with the best RRSs can be selected for an organizational portfolio model. Finally, to assess the solution method and the proposed model, the empirical result and sensitivity analysis are carried out. Ten large-scale high-rise building projects and their associated risks are evaluated as cases in this study.

Keywords

  • building engineering
  • fuzzy system
  • portfolio selection
  • project risk management

1. Introduction

The purpose of the risk management framework is to assist the organization in integrating risk management into significant activities and functions. The effectiveness of risk management will depend on its integration into the governance of the organization, including decision-making. This requires support from stakeholders, particularly top management. Framework development encompasses integrating, designing, implementing, evaluating and improving risk management across the organization.

Managing risks at all levels is an active process involving continuous planning, analysis, response, and monitoring and control. The execution of response strategies should be anticipatory and implemented by trigger events that launch response actions before the risk materializes so that opportunities (positive risks) may be enhanced or threats (negative risks) may be diminished. Even within an active process of continuous risk identification, risk management at the program, project, and operations areas are traditionally approached from a prescriptive, process-based perspective. However, within complex systems such as portfolios, risks may not be managed in the traditional or simple sense. Complexity requires a less prescriptive approach. In many cases, the execution of risk response strategies at the portfolio level involves the establishment of projects within the portfolio’s component programs or as part of continuing operations to address specific opportunities or threats (positive or negative risks) that have either materialized or have had a significant increase in the probability of occurrence as indicated by a trigger event occurring. There is an important distinction between portfolio risk management and risk management at the program or project level. In many cases, the portfolio manager should delegate risk response measures to subordinate programs or projects within the portfolio. A desired outcome from portfolio risk management is to utilize a structured risk planning and response effort in order to reduce management inaction and decision delay. Risk identification analysis and response planning acknowledge the limits of data and the lack of clear, unambiguous, and actionable information concerning many management factors at the portfolio level. Various possible risk scenarios are studied and response plans developed to limit the impact of the data and information disconnect described above. Through portfolio risk management, senior leadership and portfolio management staff are provided with courses of action or management options that assist in making decisions involving risk with incomplete information.

The importance of an appropriate selection of one project due to the combination of the selected projects for successful portfolio management is inevitable. Many companies try to implement a group of relevant projects as a portfolio to satisfy their synergy and economize their cost through efficient project management. Furthermore, it is needed to manage the risks of each project through the standard risk management process after the creation of the appropriate portfolio. The portfolio has an important role in managing a group of relevant projects so that they bring benefits and values. In the portfolio level, risk management requires a balanced attitude and management judgment exercises in two stages: the first stage is associated with the portfolio creation phase and the second one is allocated to the implementation phase of portfolio projects. We only benefit from the synergy and saving resulted from the portfolios projects management in the case of active risk management. A risk strategy response (RSS) is one of the most important processes of risk management. Therefore, selecting the appropriate projects and managing project risks are simultaneously two appropriate approaches to increase both revenue and profits of project-based organizations. In this research, the main aim is to choose an optimum portfolio of project investment considering its risk response cost and multi-term planning. Project portfolio selection observes the organization’s objectives in a planning horizon without outpacing available resources. Schniederjans and Santhanam [1] classified the system’s objectives and preferences as financial benefits, intangible benefits, availability of resources, and risk level of the project portfolio, so project risk assessment was a key element in their study [2].

Badri et al. [3] presented a binary goal programming model for the project selection of an information system. Wei and Chang [4] presented a portfolio choice model based on enterprise strategy considering customer’s resource and capability, project performance and project delivery, and project risk constraints. Project risks are categorized into three types: market risk, technical risk, financial risk. In any aspect of a project, risk can emerge. The nature of risk is uncertainty. For each project, risks should be identified and analyzed, and to cope with these risks, proper RRSs must be employed [5, 6, 7, 8, 9, 10, 11]. Tang et al. [9] developed a new solution method to the lean 6-sigma portfolio management as a binary quadratic programming problem. Muriana and Vizzini [12] presented a certain method to determine the risk of the Work Progress Status for assessing and preventing project risk.

On the other hand, Rahimi et al. [13] proposed a mathematical model, in which different risks are considered for activities so that different responses can be selected for each risk. Also, the risk responses are not considered as independent, and responses are associated with each other. Indeed, choosing the responses, which overlap each other, can affect their results, time, cost, and quality of the project. The objective function used different evaluation criteria and tried to choose the optimum responses, which maximizes these evaluation criteria. Ben-David and Raz [14] considered the cost of implementing strategies and incorporated them into an RRS selection problem. Ben-David et al. [15] extended their previous work by providing a mathematical model that facilitates computer implementation of the model. Because of the risk abatement actions, a selection problem is a complex one. Therefore, they proposed a branch-and-bound algorithm and two heuristic algorithms [16, 17]. Zhang and Fan [18] integrated all three key elements in project management (i.e., project expenditure, project planning horizon, and project quality). They proposed a new efficient solution for the mathematical model of the RRS.

Reviewing the aforementioned discussions and literature, we understand that there are gaps in (1) selecting the best projects portfolio that the effect of risk in selected projects is controlled [18], and (2) selecting projects to check the balance between the total cost of the selected projects and the profit of the selected projects, and all the predicted risk response effects. Furthermore, some of the parameters in the real-world are uncertain and can cause a high degree of uncertainty on a designed network [19].

To overcome and fulfill these gaps, for the first time, we develop a mathematical model for selecting the best projects and control risks of each selected projects under uncertainty. In this research, we investigate the trade-off between the total cost of the selected projects including all three types of resources (e.g., human, machine, raw materials) and implanting proper risk responses-and the net profit of the selected projects, and all the approximated risk response effects. The important items which this research contributes are as follows:

  • Presenting a new two-objective binary mathematical model to choose an optimum portfolio and control risks of the selected projects.

  • Introducing a new objective function for selecting projects with the maximum net profit and all the estimated risk response effects for each project.

  • Developing a new multi-period, multi-project, and multi-resource model to control risks of the selected projects.

Advertisement

2. Problem description

We present a new model to select an optimum project portfolio tacking into account many constraints in the multi-period planning horizon. Also, this model can be used to select the RRSs. The portfolio selection problem of the project RRSs is combined with four basic concepts (i.e., project opportunity, work breakdown structure, risk event, and risk responses) as well as three key elements (i.e., schedule, quality, and cost) are considered in these concepts. These concepts are described as project scope, work breakdown structure, risk event, risk response. There is a strategy to respond r risk events. On the other hand, N project should be evaluated with their risk responses’ effects to select an optimum portfolio. The optimal portfolio will be top j projects. All parameters of the mathematical model change dynamically. In this model, an optimum portfolio is selected considering its risk response expenditure. The most enticing RRSs can be acquired by solving the mathematical model. Figure 1 depicts the process of portfolio RRSs.

Figure 1.

Process of portfolio RRSs.

In this section, we present notations and mathematical modeling in Sections 2.1 and 2.2, respectively.

It should also be mentioned that the definition of parameters of sarw, srw,qarw,εw,δw,T´max,Qmax,ear,qrw,M¯, M can be found in Rahimi et al. [13]. Following is the mathematical mode.

2.1 Mathematical programming

MaxZ1=t=1Tj=1nxjt×pjt+j=1na=1Ar=1Rzjar×earE1
MinZ2=t=1Tj=1nxjti=1mhij.Cit+t=1Tj=1nxjtk=1smkj.Ckt+t=1Tj=1nxjto=1zroj.Cot+j=1na=1ACamaxrzjarE2

s.t.;

t=1Txjt1;jE3
t=1Tt+djt.xjtT+1+Tmax;jE4
j=1nhijxjtHit;i,tE5
j=1nmkjxjtMkt;k,tE6
j=1nrojxjtRot;O,tE7
i=1mhij.Cit+k=1smkj.Ckt+o=1zroj.Cot×xjt<pjt,j=1,2,,n;tE8
j=1na=1ACamaxrzjar+i=1mhijCit+k=1smkjCkt+o=1zCotroj×xjtBjt;r,j,tE9
r=1Rsrwr=1Ra=1Asarwzjarεw;j,wE10
r=1Rqrwr=1Ra=1Aqarwzjarδw;j,wE11
r=1RsrWr=1Ra=1AsarWzjarT´max;j=nE12
r=1RqrWr=1Ra=1AqarWzjarQmax;j=nE13
j=1nxjt.MARRtIjt0;tE14
j=1nxjt0;tE15
zjar+zjar´´1AaAa´M;j,a,a´,r,r´E16
zjar+zjar´´=1AaAa´M;j,a,a´,r,r´E17
zjarzjar´´0AaAa´M¯;j,a,a´,r,r´E18
zjar,zjar´´01;j,a,a´,r,r´E19
xjt01;j,tE20

Objective function value (OFV) (1) maximizes the NP of the selected portfolio and effects on all RRSa for each project of the selected portfolio. Objective function value (2) is minimizing the total cost of the chosen projects consisting of four terms. These terms are the human resource expenditure, the machine resource expenditure, the raw materials resource cost, and implementing the RRSs, respectively.

Constraint (3) ensures that each project selection will happen only one time on the planning horizon. Constraint (4) states that the completion time of each selected project is less than the planning horizon plus the upper bound for project delivery delay. Constraints (5)–(7) define the maximum limits of all three resources. Constraint (5) states that the number of human resources of all types needed for projects during selection cannot exceed the maximum available human resources for all types and all planning terms. Constraint (6) ensures that all machine-hour resources of all types needed for projects during selection do not exceed the maximum available machine-hour resources for all types and all planning terms. Constraint (7) ensures that all raw materials resources of all types needed for projects during selection do not exceed the maximum available raw materials resources of all types and for all planning terms. Constraint (8) certifies that the total cost of each selected project is less than its net profit for all planning terms. Constraint (9) certifies that the total cost of a selected project including human resource expenditure, machine resource expenditure, raw material cost, and implementing the RRSs, is less than its budget for all projects and all planning terms.

Constraint (10) certifies that, in each project, each work packages (except the last one) is completed in the due date, otherwise (if it takes more), it does not affect the schedule of its successors’ start times. Constraint (11) ensures that, in each project, each work packages (except the last one) maintain a certain level of quality. Constraint (12) indicates that, in each project, the last work package must be finished in the project deadline. Constraint (13) indicates that in each project, the last work packages must conform to project quality standards. Constraint (14) ensures if a project is selected, it is attractive and that means the internal RoR of the chosen projects should be greater than or equal to the MARR. Constraint (15) indicates that in each period, projects can be chosen. Constraints (16)–(18) are about strategies. Constraint (16) ensures that strategiesAa, and Aa´prevent each other for each project. Constraint (17) ensures that for each project, only one strategy must be selected if strategiesAa, and Aa´exclude each other. Constraint (18) states that projects cooperate if one strategy is chosen another strategy must be chosen too. Also, in constraint (19) attributes a binary variable for each project. Constraint (20) refers to binary decision variables.

2.2 Proposed uncertainty programming

Uncertainty in data can be grouped into two categories: randomness and fuzziness. Randomness originates from the random nature of data and Fuzziness refers to the vague parameters Infected with epistemic uncertainty-ambiguity of these parameters stems from the lack of knowledge regarding the exact value of these parameters. The proposed model for this problem is a fuzzy multi-objective non-linear programming (FMONLP). There are a number of adopted methods to transform this model into its equivalent crisp match, from which a two-phase approach is offered [13, 14, 15, 16, 17, 18, 19, 20]. Firstly, using an efficient method introduced by Jimenez et al., [21], the basic model is transformed into an equivalent auxiliary crisp multi-objective model. Secondly, the fuzzy aggregation function, developed by [20], is used to solve the crisp multi-objective mode. To do this, a single-objective parametric model to find the final preferred compromise solution replaces the crisp multi-objective model.

Several methods have been proposed to convert a probabilistic model into an equivalent non-probabilistic one. Probabilistic constraints transform into non-probabilistic ones using fuzzy measures, which was introduced, in the literature review section. The possibility (Pos) and necessity (Nec) are the general fuzzy measures respectively showing the optimistic and pessimistic attitudes of the decision maker. The Pos measure shows the possibility degree of occurrence of a probabilistic event, and the Nec measure indicates the minimum possibility degree of occurrence of a probabilistic event. Certainty degree of occurrence of an uncertain event is measured by credibility (Cr), which equals the average of the Pos and Nec measures [22]. New fuzzy measure Me, which is a developed Cr measure is presented by [23]. The main advantage of this measure is its flexibility to avoid excessive views. In the following, the three measures of a fuzzy event, including possibility, necessity and credibility, are described. Variable ξ is determined as a fuzzy variable on probabilistic space ΘPΘPosand its membership function, obtained from the probability measure Pos, is as follows:

X=PosθΘξθ=x,xRE21

Set A is inPΘ. The necessity and credibility measures of are defined as follows:

NecA=1PosAcE22
CrA=12PosA+NecAE23

More details and descriptions of the fuzzy theory are explained in [22]. In this research, the Me-based probabilistic programming method is selected to deal with the uncertain parameters of the presented model. The fuzzy measure Me is defined, according to [22], as follows:

MeA=NecA+EPosANecAE24

Where ε as a parameter shows the optimistic-pessimistic attitude of a decision maker. Mathematical programming problem (25) with fuzzy parameters is as follows:

Minfxc

Subjected to

AxbE25
Nxd
x0

In this notationc=c1c2cn,A=aijm×n,N=nijm×n,b=b1b1bntand d=d1d1dnt represent the triangular fuzzy numbers which are used in the objective function and constraints, respectively. Furthermore, the fuzzy number x=x1x1xn is the crisp decision vector, which shows the possibility distribution for fuzzy parameters.

To deal with the probabilistic objective functions and constraints, the expected value and chance-constrained operators based on the Me measure in this method are used. Accordingly, we can rewrite this model (26) as below:

MinEfxc

Subjected to

MeAxbαE26
MeNxbβ
x0

In this notation, E is the expected value operator, α and β are respectively the decision maker’s minimum confidence level for satisfaction of probabilistic constraints. Jiménez et al. [21] defined the expected value operator based on Me measure as follows:

Eξ=1ε2ξ1+12ξ2+ε2ξ3E27

According to [22] we can transform the aforementioned model (26) into two approximation models including the upper approximation model (UAM) and the lower approximation model (LAM). These models are presented as follows:

UAMmin1ε2c1+12c2+ε2c3xA2x+1αA3A2xb21αb2b1N2x1βN2N1xd2+1αd3d2E28
LAMmin1ε2c1+12c2+ε2c3xA2x+αA3A2xb2+1αb3b2N2x+1βN3N2xd2+βd2d1E29

Where ε is the optimistic-pessimistic parameter. Solving the LAM and UAM models provides the decision maker with the lower and upper bound of the optimal decision respectively. In this research, we use UAM models to solve problem. Accordingly, the auxiliary crisp equivalent of the presented model with triangular fuzzy parameters is presented as follows:

UAM:

MaxZ1=t=1Tj=1nxjt×1ε2pjt1+12pjt2+ε2pjt3+j=1na=1Ar=1Rzjar×1ε2ear1+12ear2+ε2ear3E30
MinZ2=t=1Tj=1nxjti=1mhij.1ε2Cit1+12Cit2+ε2Cit3+t=1Tj=1nxjtk=1smkj.1ε2Ckt1+12Ckt2+ε2ckt3+t=1Tj=1nxjto=1zroj.1ε2Cot1+12Cot2+ε2Cot3+j=1na=1A1ε2Ca1+12Ca2+ε2Ca3maxrzjarE31

Subjected to

i=1mhij.Cit2x1βCit2Cit1+k=1smkj.Ckt2x1βCkt2Ckt1+o=1zroj.Cot2x1βCot2Cot1×xjtpjt2+1βpij3pij2E32
j=1na=1ACa2x1βCa2Ca1maxrzjar+i=1mhijCit2x1βCit2Cit1+k=1smkjCkt2x1βCkt2Ckt1+o=1zCot2x1βCot2Cot1roj×xjtBjt2+1βBij3Bij2E33

Other Constraints

2.3 LAM

MaxEZ1E34
MinEZ2E35

Subjected to

i=1mhij.Cit2+1βCit3Cit2+k=1smkj.Ckt2+1βCkt3Ckt2+o=1zroj.Cot2+1βCot3Cot2×xjtpjt2βpij2pij1E36
j=1na=1ACa2+1βCa3Ca2maxrzjar+i=1mhijCit2+1βCit3Cit2+k=1smkjCkt2+1βCkt3Ckt2+o=1zCot2+1βCot3Cot2roj×xjtBjt2βBij2Bij1E37

Other Constraints

2.4 Experimental results

The select Portfolio RRSs proposed in this study is a mixed-integer linear programming model. It worth noting that the general algebraic modeling system (GAMS) software is used to solve the mathematical model. In this section, a P.G. company (One of the huge companies in the field of construction) in Iran is investigated as a real-case study to validate the performance of the proposed select Portfolio RRSs model.

An efficient multi-objective method can be done as an efficient method for obtaining the satisfaction level for each OFVs according to the decision maker’s preferences. For further explanations, the interested reader can refer to TH [20]. Two parameters in this method are very critical: relative importance of OFVs (i.e., weight factor) and coefficient of compensation. Details of the distribution functions of the parameters and the size of test problems are listed in Table 1. After that, the results on test problems for diverse values of ϑ andφ are shown in Table 2.

ParametersValues
First ProblemSecond ProblemThird Problem
J333
I202020
K333
O222
T555
W121212
R121212
A888
pjt(2 × 104,3.5 × 104)(4 × 104,6 × 104)(6 × 104,9 × 104)
ear(5 × 103,104)(8 × 103,2 × 104)(1.8 × 104,5 × 104)
Ca(103,5 × 103)(104,2 × 104)(3 × 104,5 × 104)
Bjt(5 × 103,1.5 × 104)(3 × 104,5 × 104)(5 × 104,7.5 × 104)
Cit(500,700)(800,1000)(1500,2000)
Ckt(800,1500)(2000,3000)(4000,8000)
Cot(1000,2000)(1000,2000)(1000,2000)

Table 1.

Amount of the parameters by random generation.

Problem No.ϑφZ1μ1ZZ2μ2Z
10.60.3,0.733218.20.924781.080.973
0.60.5,0.532039.20.958817.200.930
0.60.7,0.331287.40.981826.980.919
0.40.3,0.734838.80.881772.350.984
0.40.5,0.532791.60.936805.930.943
0.40.7,0.330909.30.994867.570.876
20.60.3,0.750448.40.8921317.20.911
0.60.5,0.548966.20.9191345.30.890
0.60.7,0.346632.10.9651415.00.848
0.40.3,0.753507.70.8411248.60.961
0.40.5,0.551903.10.8671295.80.926
0.40.7,0.347418.30.9491393.70.861
30.60.3,0.770806.10.9182098.60.953
0.60.5,0.569370.30.9372164.50.924
0.60.7,0.367427.30.9642171.50.921
0.40.3,0.771982.20.9032044.90.978
0.40.5,0.569817.40.9312148.20.931
0.40.7,0.366598.30.9762229.60.897

Table 2.

Results of test problem 1 (β=0.5).

According to Table 2, the values of objective functions change based on the value of ϑ. The results indicate that satisfaction degrees displaying each objective function change based on the value of ϑ. In this table, the values of satisfaction degree of objective functions (1) and (2) for test problem 2 fluctuate between 0.841 and 0.965, and 0.848 and 0.961, respectively. The results show that by manipulating the value of ϑ, the decision-maker can make trade-offs between two objective functions and select an optimal pair. Generally, increasing the value of ϑ leads to higher allocated weights to acquire a higher lower bound for the satisfaction degree of objectives (λ0).

Based on the acquired results and considering the budget and time limitations, the most appropriate strategy for responding to the risk work packages is provided in Table 3. In this test problem project 8 and 3 are selected. Appendix A. shows the amount of maximum allowed time reduction (day) and the quality of each activity (in percentage). The obtained quality of each activity under acceptable and ideal condition is assumed 90% and 99% respectively (δw1%10%). Appendix B. illustrates the effect of implementing risk response strategies on risks cost reduction (if occurs).

Optimal allocation in project 3RisksWork Packages (WP)
RR 27R1WP 1- WP 10
RR 17R 5WP 5- WP 10
RR 21R 8WP 5- WP 10
RR 10R 9WP 3- WP 4
RR 12R 12WP 1, WP 9, WP 10
RR 7R 24WP 2- WP 8
RR 22R 25WP 4- WP 6
RR 1R 26WP 6, WP 7, WP 9
Optimal allocation in project 3RisksWork packages
RRS 27R 1WP 1- WP 12
RRS 13R 2WP 1, WP 3- WP 10
RRS 14R 4WP 2- WP 12
RRS 11R 7WP 3- WP 12
RRS 21R 8WP 5- WP 12
RRS 10R 9WP 5- WP 12
RRS 30R 10WP 8, WP 10, WP 11
RRS 16R 11WP 3- WP 12

Table 3.

Solution allocation of RRs for projects 8 and 3.

2.5 Managerial insights

Large construction companies mainly use the project to carry out their activities. Due to the limited resources of these companies, which can be considered project-based organizations, they have to decide on selecting, stopping projects and allocating resources, and have using portfolio management tools, consequently. Portfolio Risk Management is one of the common knowledge scopes in portfolio management with project portfolio decisions application. The primary purpose of risk management is to protect the organization against damages and to prepare the organization for possible future damage. Therefore, the risks should be met with proper risk responses. Risk management at the portfolio level supports the aforementioned goals in different ways.

Firstly, enables the portfolio manager to compare the risks of single projects in terms of risk feature reduction actions. This comparison allows to make difference between options and the single risk levels are clarified and the results of risk responses actions are reflected and facilitate the transfer of experiences between the projects. Secondly, the comparison of the public risks of the portfolio and its trend according to the life cycle of the project has been revealed. Clarity growth leads to preventing other project risks or increasing focus on risks that are prevalent in most of the projects. Thirdly, risk management reduces uncertainty by providing enough information to make decisions. As a result, estimations are more accurate, reliable, and reduce the chance of surprise and the rate of failures. Therefore, risk management should increase information clarity, detecting and clarifying problems, risk response capacity, and depth of information for decision making.

Advertisement

3. Conclusion

In this research, a linear mixed-integer model was proposed to solve a project selection problem and provide RRSs. According to objective functions, this model firstly aims to select projects with the highest net profit and risk response effects. Secondly, these projects should be carried out with minimum resource and implanting risk responses costs. The model is solved to select the most desirable projects and risk response strategies to deal with risk events. The main contribution of this research is combining of project selection from a portfolio and calculation of risk response effect. In addition, because of environmental effects, some parameters (including the cost of human, machine, material, risk response effect, etc.) were considered as fuzzy numbers. Fuzzy Me measure is considered to deal with the uncertain parameters of the proposed model. To solve the model ten building project were studied, and Net profit and resources costs were considered as objective functions. Finally, optimal allocation of risk response strategies was determined. TH method was used to solve the model, which was coded in GAMS. Results showed that increasing budgets in sample problem, led to higher net profit and less projects costs. The sensitivity analysis of the case study showed the necessity of the trade-offs between maximizing profit and minimizing projects cost. At last, Pareto frontier was analyzed. Results indicate that this model can act as a powerful criterion and help project managers to increase desirable impacts of a solution before implementing the project. Also, uncertain parameters like robust programming can be determined to cover the limitations of the designed model. Moreover, since the presented model is categorized as an NP-hard problem, meta-heuristic algorithms may be utilized to solve the model.

Advertisement

Advertisement

Appendix A.1

Project 1Project 2
W1W2W3W4W5W6W7W8W9W1W2W3W4W5W6W7
δw10%10%10%10%10%10%10%10%10%10%10%10%10%10%10%10%
εw14810151081414121411141111118
Cit22,000 (USD)25,000(USD)
Ckt35,000 (USD)30,000(USD)
Cot30,000 (USD)38,000(USD)
Bjt200 million (USD)250 million (USD)

Advertisement

Appendix A.2

Project 3
W1W2W3W4W5W6W7W8W9W10W11W12
δw10%10%10%10%10%10%10%10%10%10%10%10%
εw1112141012139131510814
Cit20,000 (USD)
Ckt35,000 (USD)
Cot28,000 (USD)
Bjt270 million (USD)

Advertisement

Appendix A.3

Project 4Project 5Project 6
W1W2W3W4W5W6W7W1W2W3W4W5W6W1W2W3W4W5
δw10%10%10%11%10%10%10%10%10%10%10%10%10%10%10%10%10%10%
εw101012121391012139131410101212149
Cit25,000 (USD)25,000 (USD)20,000 (USD)
Ckt30,000 (USD)35,000 (USD)35,000 (USD)
Cot35,000 (USD)35,000 (USD)38,000 (USD)
Bjt200 million (USD)200 million (USD)250 million (USD)

Advertisement

Appendix A.4

Project 7
W1W2W3W4W5W6W7W8
δw10%10%10%10%10%10%10%10%
εw811141113131214
Cit25,000 (USD)
Ckt45,000 (USD)
Cot28,000 (USD)
Bjt300 million (USD)

Advertisement

Appendix A.5

Project 8Project 9
W1W2W3W4W5W6W7W8W9W10W1W2W3W4W5W6W7
δw10%10%10%10%10%10%10%10%10%10%11%11%11%11%11%11%11%
εw1415141614111291414101213913159
Cit20,000(USD)20,000(USD)
Ckt35,000(USD)38,000(USD)
Cot25,000(USD)40,000(USD)
Bjt200 million (USD)200 million (USD)

Advertisement

Appendix A.6

Project 10
W1W2W3W4W5W6W7W8W9
δw10%10%10%10%10%10%10%10%10%
εw11118111214101213
Cit25,000(USD)
Ckt35,000(USD)
Cot28,000(USD)
Bjt250 million (USD)

Appendix B.1

Risks
Risk 1Risk 2Risk 3Risk 4Risk 5Risk 6Risk 7Risk 8Risk 9Risk 10
Risk responses strategiesRisk Response 133207260
Risk Response 245307310
Risk Response 3948047905460445010,020
Risk Response 452305960
Risk Response 538005010
Risk Response 6614056306730
Risk Response 7584050408300
Risk Response 848007100
Risk Response 9710039606200
Risk Response 10798045609200
Risk Response 1143205070890040708090
Risk Response 12975010,45064705300
Risk Response 1378904600480045004750
Risk Response 144200654098006540489047509640
Risk Response 15694073104800
Risk Response 1654704580670011,23045004980
Risk Response 1748609870780069407500
Risk Response 187560746086007120
Risk Response 19398046906400
Risk Response 20731046005600
Risk Response 2157409000751045004500
Risk Response 226210467048106070
Risk Response 234670790098007240
Risk Response 244120398056003650
Risk Response 2578204680780010,110
Risk Response 266450821080908000
Risk Response 2792006480404052004860
Risk Response 28639049207500
Risk Response 29589064007560
Risk Response 304620398065404890404010,200
Risk Response 3172007560756039607200

Appendix B.2

Risks
Risk 11Risk 12Risk 13Risk 14Risk 15Risk 16
Risk responses strategiesRisk Response 1930072004620
Risk Response 245503500
Risk Response 33900
Risk Response 47220789035604780
Risk Response 595208630
Risk Response 6
Risk Response 797007560
Risk Response 8820092004560
Risk Response 9940056707200
Risk Response 10750010,40011,630475096007450
Risk Response 11504075008040
Risk Response 1211,2307400
Risk Response 137800
Risk Response 148750462010,400
Risk Response 1512,400459068704700
Risk Response 16950010,400
Risk Response 1778009500
Risk Response 1886007500
Risk Response 198620
Risk Response 20560095008720
Risk Response 217120
Risk Response 2248109450
Risk Response 2382008620
Risk Response 2410,4108300
Risk Response 2510,420
Risk Response 2678004860
Risk Response 2786008200
Risk Response 288400
Risk Response 2946805600456011,11012,300
Risk Response 3075108600
Risk Response 314810

Appendix B.3

Risks
Risk 17Risk 18Risk 19Risk 19Risk 20Risk 21Risk 22Risk 23Risk 24
Risk responses strategiesRisk Response 133207260
Risk Response 2473041208510
Risk Response 34850467042304450
Risk Response 456307640
Risk Response 557005410
Risk Response 651006730
Risk Response 7522040408300
Risk Response 842107100
Risk Response 99000469010,200900033204800
Risk Response 1042504670745073104870
Risk Response 119800851047007200
Risk Response 12960048404500
Risk Response 1346807890712046805700
Risk Response 1456006400
Risk Response 15468067305220
Risk Response 16492074204920
Risk Response 1747606900710060706780
Risk Response 18623072404250
Risk Response 19552012,4004700
Risk Response 20489048706970
Risk Response 2196408010
Risk Response 22671010,7005400
Risk Response 236200780047909870
Risk Response 243750892065405470
Risk Response 2547903450
Risk Response 269760450011,4504800
Risk Response 2774507890
Risk Response 28896047509700
Risk Response 2942004300478074504600
Risk Response 30671010,0104500
Risk Response 317890720098008040

Appendix B.4

Risks
Risk 24Risk 25Risk 26Risk 27Risk 28Risk 29Risk 30Risk 31Risk 32Risk 33
Risk responses strategiesRisk Response 1950078007800
Risk Response 2900042003320
Risk Response 393204670
Risk Response 4862097004230
Risk Response 5952010,400
Risk Response 65700
Risk Response 78300970051007890
Risk Response 882009200547052208090
Risk Response 9480045804920
Risk Response 10740075004750
Risk Response 1165206970687042509840
Risk Response 12450045808510809012,300
Risk Response 136980
Risk Response 1473104750
Risk Response 154500412096407560
Risk Response 1674503640480075404520
Risk Response 1767807120642092006420
Risk Response 186400348041207890
Risk Response 194700809058003320
Risk Response 206970478067006340
Risk Response 214750607069804120
Risk Response 229640724010,230
Risk Response 23489078905700
Risk Response 24547011,1006420
Risk Response 258000698095605220
Risk Response 26789047806340
Risk Response 277800
Risk Response 287450987010,500
Risk Response 2946008000632089706740
Risk Response 30712097806700
Risk Response 3157007400

Notations

Sets

j

Projects j=1,2,,n).

i

Human resources (HR)i=12m.

k

Machinery k=12s.

O

Material O=12z.

t

Time period t=12T.

w

Work packagesw=12W.

r

Risk events (RE)r=12R.

a

Candidate RRSsa=12A.

Parameters

Hit

Max accessible HR i in time t (person-hours).

hij

Demand of HR i in j (person-hours).

Mkt

Max available machine-hour k in time t.

mkj

Demand of machine-hour k in j.

Rot

Max accessible material o in time t.

roj

Demand of material o in j.

Bjt

Maximum available project budget for j in period t.

Cit

Hourly cost of HR i in period t.

Ckt

Hourly cost of machine k in time t.

Cot

Unit cost of material o in timet .

Ww

Work packages w.

Rr

Risk response (RR) r.

Aa

Candidate RRS a.

Ca

Cost of implementing risk response strategy a.

pjt

Total Net Profit (NP) worth of j in time t.

Ijt

RoR for j in time t.

MARRt

MARR during period t.

djt

Period of project j in time t.

Decision variables

xjt

if project j is chosen for investment in time t, 1; otherwise, 0.

zjar

1 if RRS a is applied for RE r for project j; 0, otherwise.

References

  1. 1. Schniederjans, M. J., & Santhanam, R. (1993). A multi-objective constrained resource information system project selection method. European Journal of Operational Research, 70(2), 244–253
  2. 2. Ahmad, Z., Thaheem, M. J., & Maqsoom, A. (2018). Building information modeling as a risk transformer: An evolutionary insight into the project uncertainty. Automation in Construction, 92, 103–119
  3. 3. Badri, M. A., Davis, D., & Davis, D. (2001). A comprehensive 0–1 goal-programming model for project selection. International Journal of Project Management, 19(4), 243–252
  4. 4. Wei, C.-C., & Chang, H.-W. (2011). A new approach for selecting portfolio of new product development projects. Expert Systems with Applications, 38(1), 429–434
  5. 5. Zou, P. X., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601–614
  6. 6. Ebrahimnejad, S., Mousavi, S. M., & Mojtahedi, S. M. H. (2008, December). A fuzzy BOT project risk evaluation model in Iranian power plant industry. In Industrial Engineering and Engineering Management, 2008. IEEM 2008. IEEE International Conference on (pp. 1038–1042). IEEE
  7. 7. Mousavi, S. M., Malekly, H., Hashemi, H., & Mojtahedi, S. M. H. (2008, December). A two-phase fuzzy decision-making methodology for bridge scheme selection. In Industrial Engineering and Engineering Management, 2008. IEEM 2008. IEEE International Conference on (pp. 415–419). IEEE
  8. 8. Alborzi, S., Aminian, A., Mojtahedi, S. M. H., & Mousavi, S. M. (2008, December). An analysis of project risks using the non-parametric bootstrap technique. In Industrial Engineering and Engineering Management, 2008. IEEM 2008. IEEE International Conference on (pp. 1295–1299). IEEE
  9. 9. Tang, W., Qiang, M., Duffield, C. F., Young, D. M., & Lu, Y. (2007). Risk management in the Chinese construction industry. Journal of construction engineering and management, 133(12), 944–956
  10. 10. Mousavi, S. M., Tavakkoli-Moghaddam, R., Hashemi, H., & Mojtahedi, S.M.H. (2011). A novel approach based on non-parametric resampling with the interval analysis for large engineering project risks. Safety Science, 49(10), 1340–1348
  11. 11. Ebrahimnejad, S., Mousavi, S.M., Tavakkoli-Moghaddam, R., & Heydar, M. (2014). Risk ranking in mega projects by fuzzy compromise approach: A comparative analysis. Journal of Intelligent and Fuzzy Systems, 26(2), 949–959
  12. 12. Muriana, C., & Vizzini, G. (2017). Project risk management: A deterministic quantitative technique for assessment and mitigation. International Journal of Project Management, 35(3), 320–340
  13. 13. Rahimi, Y., Tavakkoli-Moghaddam, R., Iranmanesh, S. H., & Vaez-Alaei, M. (2018). Hybrid approach to construction project risk management with simultaneous FMEA/ISO 31000/evolutionary algorithms: Empirical optimization study. Journal of Construction Engineering and Management, 144(6), 04018043
  14. 14. Ben-David, I., & Raz, T. (2001). An integrated approach for risk response development in project planning. Journal of the Operational Research Society, 52(1), 14–25
  15. 15. Ben-David, I., Rabinowitz, G., & Raz, T. (2002). Economic optimization of project risk management efforts. Project Risk Management Optimization
  16. 16. Khodemani-Yazdi, M., Tavakkoli-Moghaddam, R., Bashiri, M., & Rahimi, Y. (2019). Solving a new bi-objective hierarchical hub location problem with an M∕ M∕ c queuing framework. Engineering Applications of Artificial Intelligence, 78, 53–70
  17. 17. Roshan, M., Tavakkoli-Moghaddam, R., & Rahimi, Y. (2019). A two-stage approach to agile pharmaceutical supply chain management with product substitutability in crises. Computers & Chemical Engineering, 127, 200–217
  18. 18. Zhang, Y., & Fan, Z.-P. (2014). An optimization method for selecting project risk response. International Journal of Project Management, 32(3), 412–422
  19. 19. Zhalechian, M., Tavakkoli-Moghaddam, R., & Rahimi, Y. (2017). A self-adaptive evolutionary algorithm for a fuzzy multi-objective hub location problem: An integration of responsiveness and social responsibility. Engineering Applications of Artificial Intelligence, 62, 1–16
  20. 20. Torabi, S. A., & Hassini, E. (2008). An interactive possibilistic programming approach for multiple objective supply chain master planning. Fuzzy sets and systems, 159(2), 193–214
  21. 21. Jiménez, M., Arenas, M., Bilbao, A., & Rodrı, M. V. (2007). Linear programming with fuzzy parameters: an interactive method resolution. European Journal of Operational Research, 177(3), 1599–1609
  22. 22. Pishvaee, M. S., Torabi, S. A., & Razmi, J. (2012). Credibility-based fuzzy mathematical programming model for green logistics design under uncertainty. Computers & Industrial Engineering, 62(2), 624–632
  23. 23. Xu, J., & Zhou, X. (2013). Approximation based fuzzy multi-objective models with expected objectives and chance constraints: Application to earth-rock work allocation. Information Sciences, 238, 75–95